OPTIMIZATION OF ENGINE SERVICE TIME SYSTEM AND P2H ON OHT CAT 777 HEAVY EQUIPMENT AT PT. SITUS SAPTAINDRA SEJATI ADMO SOUTH KALIMANTAN

Keywords:
Optimization, PERT, CPM, critical PathAbstract
PT. Saptaindra Sejati is a coal contractor that has a fleet of heavy equipment Dump trucks OHT Cat 777, used to transport coal mining materials from the mining location to the precessing location. In order to support operasional activities, a good fleet of heavy equipmeny id needed equipment id needed so that the coal production target is achieved properly, a maintenance process is needed, because the condition of tne Dump Truck OHT Cat 777 still often experiences damage. With the aim of optimizing the engine service time system and P2H on the OHT Cat 777 heavy equipment. The methods used are PERT and CPM. The results of the analysis with the PERT method are 173,3 minutes, while using the CPM method 170 minutes with the critical path A-B-C-D-E-F-G-H-I-K-L-M-N-O-P-Q-R. In the p2H activity, the engine area uses the PERT method 72,99 minutes while with the CPM method 72 minutes. The critical path generated from both methods has similarities, namely A-H-I-K-G-J-L. The CPM method is faster in terms of work duration and better in its application. The influencing factor is the sequence of work that is adjusted to the network planning so that workers and companies can know which activities need to be prioritized so that there are no delays in completing service engine and P2H activities
References
T. Sugiarta, “Analisis Penjadwalan Proyek Remote Terminal Unit dengan Penerapan Metode CPM dan PERT di PT. XYZ,” JIEMS (Journal Ind. Eng. Manag. Syst., vol. 14, no. 2, pp. 115–139, 2022, doi: 10.30813/jiems.v14i2.2601.
D. Hadicara and A. Rochim, “Penggunaan Metode PERT dan CPM dalam Proyek Pembangunan Jalan,” Pondasi, vol. 28, no. 1, pp. 32–44, 2023, [Online]. Available: https://jurnal.unissula.ac.id/index.php/pondasi/article/view/30148
Cucu Tarliah Dimyati, Keputusan, Operations Research : Model-Model Pengambilan. 1994.
J. Supranto, Riset Operasi untuk Pengambilan Keputusan. Jakarta UI Press, 1988.
Darsini, Penelitian Operasional I. Klaten Jawa tengah: Lakeisha, 2020. [Online]. Available: https://www.semanticscholar.org/paper/9056c0ed1129cbcf6e1957f4f9aaa1368f9540e0
S. Abadiyah;, M. A. Mu’min;, and T. D. Julianto, “Analisa Perbandingan Waktu Penjadwalan Proyek dengan Metode CPM (Critical Path Method) dan PERT (Program Evaluation Tecnique),” vol. 2, no. 2, pp. 72–79, 2020.
S. Prawirosentono, Manajemen Operasi: Analisis dan Studi Kasus. 2000.
E. Saputro, H. F. Satoto, M. Pumpungan, and J. Timur, “Implementasi dengan Metode Cpm-Pert Terhadap Penjadwalan Proses Produksi Conveyor Table Top Chain pada CV . Adikarya Teknik Sidoarjo,” vol. 3, 2025.