Analysis of Productivity of Lightweight Brick Wall Installation Work on The Construction of a Hospital with the Work Sampling Method

Keywords:
productivity, lightweight brick walls, effective, labor utilization rateAbstract
Analyzing labor productivity in construction work is very important as it greatly affects the completion time of construction projects. One of the labor-intensive jobs is the construction of lightweight brick walls. Therefore, productivity analysis is necessary for this job. This study was conducted to measure the productivity value and work utilization rate (LUR) in the National Brain Center Hospital construction project in Jakarta. A sampling method was used with on-site observation over a period of one week. The analysis showed that the average productivity value of workers constructing lightweight brick walls was 9,623 m²/day. The labor utilization rate (LUR) analysis in the construction of lightweight brick walls resulted in a value of 65%, which is higher than 50%, indicating that the construction of lightweight brick walls in this project was effective.
References
Ervianto, Wulfram I. 2002. Manajemen Proyek Konstruksi. Yogyakarta. ANDI
Umam, Roisul. 2020. Analisis Produktivitas Tukang pada Pekerjaan Dinding Bata Merah dengan Menggunakan Metode Work Sampling. Yogyakarta: UII (Skripsi).
Pawiro, S., Tjakra, J., dan Arsjad, T. T, 2015. Optimalisasi Produktivitas Tenaga Kerja dalam Proyek Konstruksi (Studi Kasus: Pembangunan Gedung Mantos Tahap III). Tekno, 13(62).
Sukirno. 2010. Makro Ekonomi Teori Pengantar. Jakarta. Raja Grasindo Perseda
Andi, A., dan Prasetya, A, 2004. Analisa Produktifitas Pekerja dengan Metode Work Sampling Studi Kasus pada Proyek X dan Y. Civil Engineering Dimension, 6(2), pp-72.
Wignjosoebroto, Sritomo. 2003. Ergonomi Studi Gerak dan Waktu, Cetakan.
Olomolaiye, P. O., Jayawardane, A. K.. W and Harris F. C. 1998. Construction Productivity Manajemen. Singapore. McGraw-Hill, inc.
Wibowo, K. D. dan Prasetya, A. 2004. Analisia Labor Utilization Rate pada proyek “X” dan “Y” dengan Menggunakan Metode Work Sampling. Surabaya. Universitas Kristrn Petra. (Skripsi).
Yanti, G, 2017. Produktivitas Tenaga Kerja dengan Metode Work Sampling Proyek Perumahan di Kota Pekan Baru. Jurnal Teknik Sipil, 3(2), 100-106.
Desfita, Mediana, dan Fadlan Hamid. 2021. Work Sampling Methods dalam Analisis Produktivitas Tenaga Kerja Kontruksi Proyek Pembangunan Gedung. Jurnal Teknologi Dan Sistem Informasi Bisnis 3.1, 259-266.
Prasetyo, D. A., Anthony, A., Chandra, H. P., dan Ratnawidjaja, S, 2017. Analisis Produktivitas Tenaga Kerja dengan Metode Work Sampling: Studi Kasus Proyek Tunjungan Plaza 6. Jurnal Dimensi Pratama Teknik Sipil, 6(1).
Hutasoit, Josua Parulian, Mochtar Sibi, dan Revo L. Inkiriwang, 2017. Analisis Produktivitas Tenaga Kerja Konstruksi pada Pekerjaan Pasangan Lantai Keramik dan Plesteran Dinding Menggunakan Metode Work Sampling (Studi Kasus: Bangunan Gedung Pendidikan Fakultas Kedokteran), Jurnal Sipil Statik 5, no. 4.
Kartika, Nia, Siti Muawanah Robial, dan Agung Pratama, 2021. Analisis Produktivitas Tenaga Kerja pada Pekerjaan Kolom di Proyek Pembangunan Gedung Pemda Kabupaten Sukabumi. JURNAL MOMEN TEKNIK SIPIL SURYAKANCANA 3, no. 2, 103-112.
Abma, Vendie, 2017. Analisis Produktivitas Tukang pada Pekerjaan Dinding Bata Merah dengan Menggunakan Metode Work Sampling.
Iroth, Vivian G., Grace Y. Malingkas, dan Jermias Tjakra. 2024. Produktivitas Tenaga Kerja pada Pekerjaan Dinding Dengan menggunakan Metode Work Sampling pada Proyek Pembangunan Ruko Cluster Amethyst Kawanua Emerald City Manado", TEKNO 22.87, 425-432